Asphalt Down

STEP 3: Drainage Improvement

Keeping water away from the roadbed is very important. Drainage ditches are either created or improved on either side of the roadway. Culverts are installed where the road crosses streams. Driveway culverts are installed as needed to improve drainage.

Dig Up the Old Culvert: Old culverts are crushed and sold for scrap, saving all of us money.

 

Remove the Old Culvert: The old culvert is placed on the side of the road for pickup later.

Install the New Culvert: The new culvert will keep water away from the road for many years!

 

STEP 4: Sub-Grade Preparation